Client approved the work then opened a dispute three weeks later, how do these actually get decided
Fixed price job, 2400, delivered in three milestones, all three approved in writing at the time. Three weeks after the final approval they opened a dispute claiming the work was never delivered to spec. Most of our conversation happened on the platform but the last month drifted to email and a couple of calls. Has anyone been through this and can tell me what the process actually looks like from the inside?
@soloseat_sana · 5mo ago · 3 replies
Disputes are decided on the evidence that exists inside the platform, which is the whole reason the platform exists. Written milestone approvals in the platform messages are strong, and the fact that they approved each one at the time is the single most useful thing you have. Pull every message, every delivery timestamp and every approval into one document now, in order, before you write anything else, because the case is usually won by whoever presents a clean timeline.
Reply
Report
@visible_stitch_vi · 4mo ago
Approvals are all there with dates. The scope discussion that led to the last milestone is unfortunately in email.
Reply
Report
@soloseat_sana · 4mo ago
Then paste the relevant email threads into a platform message now, referencing dates, so at least the content is in the record even if the original conversation was not.
Reply