Roof, wiring, plaster and windows, and budget for two of them this year, how do you sequence that
1930s semi, we can afford roughly two of the four now and the rest waits about eighteen months. Everyone says roof first, but the wiring is rubber and fabric on two circuits and the hall plaster is coming off in sheets. Nobody lives in the hall so I am tempted to leave it and put the money elsewhere. How did you sequence yours and what did waiting on the wrong thing actually cost you?
@deadline_dee · 3mo ago
Whatever you choose, group the destructive work into one window. Rewiring means chasing walls and lifting floors, replastering means dust everywhere and everything moved out, and doing those in the same eight weeks is dramatically less miserable and cheaper than doing them eighteen months apart. If you can possibly stretch to wiring and plaster together and leave the windows for later, that is the combination that saves the most, because the plasterer follows the electrician and makes good behind them.