In what order does a conversion actually go, and how many weekends is it really from empty to liveable
Empty LWB van arriving in three weeks, both of us work full time, so this is weekends and the odd evening. Every build video jumps from bare metal to a finished interior with a soundtrack, and I cannot work out what depends on what. I would like a genuine sequence and a genuine hour count from people who tracked it, even if the answer is depressing.
@kerf_wander · 3mo ago · 3 replies
The dependency chain that matters is: strip and clean, treat rust, cut every hole you will ever want including windows fan and any external inlets, sound deaden, insulate, floor, run all wiring and any plumbing routes while the walls are open, then wall and ceiling panels, then furniture, then the fiddly finishing that takes twice as long as you think. The only rule you cannot break is that anything passing through the shell or hiding behind a panel happens before that panel goes on.
Reply
Report
@psu_paula · 3mo ago
Decide now even if you fit it later. Frame around where it will go and leave the panel removable, otherwise later means never or means a very bad Saturday.
Reply
Report
@psu_paula · 3mo ago
Every hole up front is the part I was going to get wrong. I was planning to decide on the second window later.